Home / Case Study / WATER AND WASTEWATER REACTIVE
Kerridge & bollington
Working collaboratively and planning carefully to deliver 650 metres of resilient water infrastructure.
view the galleryHome / Case Study / WATER AND WASTEWATER REACTIVE
Working collaboratively and planning carefully to deliver 650 metres of resilient water infrastructure.
view the galleryOf 315mm mains replacement
Access maintained
INSTALLATION METHOD
CUSTOMER ACCOLDAES
our work
Delivering 650m of resilient water infrastructure through careful planning and close collaboration.
get it done
Following a series of high-profile bursts on an existing 10″ PVC water main, Network Plus appointed Caecillian Utilities to deliver a long-term solution for the Bollington community. Before works began, we engaged with residents and local businesses to understand their concerns and shape a programme that minimised disruption while delivering 650m of new 315mm water main.
do it right
With the main serving as a critical outlet from the local reservoir, outages were limited to six hours and supported by Alternative Supply Vehicles to maintain customer supply. Temporary overland mains, lift-and-lay installation methods and the reconstruction of an abandoned 300m access road ensured residents maintained safe, 24/7 access throughout the project.
make it count
By combining careful planning with genuine community engagement, the project was delivered successfully with minimal disruption. The scheme received 17 accolades from the 20 affected residents, and its success has led to Caecillian being invited to support the next phase of the network replacement programme.
get in touch
Tell us about the scheme and we’ll come back with the team, the plant and the plan to deliver it.
Phone:
0161 336 2665
Email:
info@caecillian.com