Working collaboratively and planning carefully to deliver 650 metres of resilient water infrastructure.

view the gallery

650m

Of 315mm mains replacement

24/7

 Access maintained

LIFT & LAY

INSTALLATION METHOD

17

CUSTOMER ACCOLDAES

our work

Recent case study

Delivering 650m of resilient water infrastructure through careful planning and close collaboration.

get it done

Following a series of high-profile bursts on an existing 10″ PVC water main, Network Plus appointed Caecillian Utilities to deliver a long-term solution for the Bollington community. Before works began, we engaged with residents and local businesses to understand their concerns and shape a programme that minimised disruption while delivering 650m of new 315mm water main.

do it right

With the main serving as a critical outlet from the local reservoir, outages were limited to six hours and supported by Alternative Supply Vehicles to maintain customer supply. Temporary overland mains, lift-and-lay installation methods and the reconstruction of an abandoned 300m access road ensured residents maintained safe, 24/7 access throughout the project.

make it count

By combining careful planning with genuine community engagement, the project was delivered successfully with minimal disruption. The scheme received 17 accolades from the 20 affected residents, and its success has led to Caecillian being invited to support the next phase of the network replacement programme.

on site

case study gallery

get in touch

Let’s talk about
your next gas
programme

Tell us about the scheme and we’ll come back with the team, the plant and the plan to deliver it.

Phone:
0161 336 2665

Email:
info@caecillian.com

Name